Answer:
applied overhead to hoses: 33,800
Explanation:
We calculate the rate by dividing the expected overhead over the cost driver:
[tex]\frac{Cost\: Of \:Manufacturing \:Overhead}{Cost \:Driver}= Overhead \:Rate[/tex]
In this case, machine hours is the cost driver:
83,200 / 3,200 = 26
now applied ovehead:
machine hours x   rate
     1,300     x   26  = 33,800