Question Completion:
2. Prepare a single journal entry to record all the incurred costs assuming they are paid in cash on January 1.
Answer:
Mitzu Co.
1. Allocation of  Appraised Value  Percent  x Total Cost    = Apportioned
Purchase Price               of Total  of Acquisition      Cost
Land           $1,799,500   59%    x  $2,750,000  =  $1,622,500
Building 2        $671,000   22%    x  $2,750,000  =    605,000
Land Improve-
ments 1         $579,500    19%    x  $2,750,000  =    522,500
Totals         $3,050,000   100%                 =  $2750,000
2. Journal Entry:
January 1:
Debit Land (demolishing Building 1) $345,000
Debit Land (additional land grading) $195,000
Debit Building 3 $2,242,000
Debit Land Improvements 2 $173,000
Credit Cash $2,955,000
To record the payment of additional costs incurred.
Explanation:
a) Data and Calculations:
Lump-sum amount paid $2,750,000
Additional costs incurred:
Land (demolishing Building 1) $345,000
Land (additional land grading) $195,000
Building 3 $2,242,000, having a useful life of 25 years and a $402,000 salvage value
Land Improvements 2 $173,000 near Building 2 having a 20-year useful life and no salvage value