Respuesta :
Solution :
Risk management first involves the identification of the potential risk that may be involved. It should focus both on the objectives as well as events that could cause the consequences.
Some of the major risks that can be involved are :
• sudden weather conditions which may not support the flight travel.
• Embargo on fishing by the State or local authority suddenly
• any kind of physical injury to the members of the group
• there may be forest fire around the lake
• technical error that might occur during the course of adventures
The impact for the risk that includes the majuere risk will be very high for all the parameters that can increase the cost by 40%, it can also lead to increase in time by about 20% which can cancel the expedition. . These types of risk will not be covered under any scope.
For the physical risk, the impact will be moderate for the parameters.
              Risk Response Matrix
Risk     Response     Contigency plan     Trigger   Who is responsible
Force     Mitigate    Choosing another    Situation is        Nils
Majuere             destination as a back  not clear in
                    up.                24 hours.
Physical  Mitigate    Proper training and   After observing    Eddie
injury              safety kits           the participants